Bitdeer Technologies Group unveils significant operational advancements, including HPC/AI strategy expansion, increased self-mining hashrate, and infrastructure updates across global sites.
Bitdeer Technologies Group, a prominent player in the Bitcoin mining industry, has announced a series of strategic updates for September 2025, according to Bitdeer Technologies Group. The company is making strides in expanding its high-performance computing (HPC) and artificial intelligence (AI) initiatives while boosting its self-mining capabilities.
HPC/AI Strategy Expansion
Bitdeer is significantly expanding its role in the HPC/AI data center market. The company has commenced design and layout planning for a new data center at Clarington, Ohio, which will initially serve Bitcoin mining but is designed to transition into an AI data center. This site will have a confirmed electrical capacity of 570 MW by Q3 2026, ahead of previous schedules.
Additionally, Bitdeer plans to convert its Tydal, Norway Phase 2 site into an AI data center by Q4 2026, supporting 164 MW of IT load. The company is also working on converting its Wenatchee site in Washington into an AI data center using modular technology. By the end of 2026, Bitdeer aims to operate over 200 MW dedicated to AI computing, with a significant portion owned by the company.
Increased Mining Capacity
The company has reported a notable increase in its self-mining hashrate to 35.0 EH/s, with plans to reach 40 EH/s by the end of October 2025. The deployment of SEALMINERs has been pivotal in this growth. Bitdeer also launched the SEALMINER A3 series, which includes both air and hydro-cooling models, achieving power efficiencies between 12.5 J/TH and 14 J/TH.
Moreover, Bitdeer has completed the first tape out of its SEAL04 chips, showing promising efficiency improvements. The company plans to continue expanding its SEALMINER fleet, leveraging its global power capacity to become one of the largest vertically integrated miners globally.
Global Infrastructure Developments
Bitdeer continues to enhance its infrastructure, with significant developments across various sites. The Tydal, Norway, and Jigmeling, Bhutan sites have completed energization, and a new 300 MW power pipeline in Niles, Ohio, was officially launched in September 2025. Bitdeer's total global power pipeline has now increased to 3 GW.
The company is also actively planning its U.S. manufacturing operations and recruiting in-house experts to support its expanded HPC/AI efforts. These developments align with Bitdeer's strategic vision to cater to the growing demand for AI computing power, which is expected to persist through 2027.
Bitdeer is poised to significantly impact the cryptocurrency and AI sectors with these initiatives, combining its mining capabilities with advanced computing solutions to drive future growth.